1. Week 2: October 8 Monday

a. Weekly team conference call at 8PM EST

2. Week 2: October 13 Saturday

a. Team blog site created and all team members successfully logged in.
i. Lissette on point for blog site


b. Rough draft of virtual landscape created in SketchUp and forwarded to team for review.
i. Brian on point for virtual landscape


c. Research the various sculptors head start
i. Nicole on point to provide research to the team about various sculptors


d. Team Charter created and added to the blog site
i. Lissette on point for the charter


3. Week 3: October 15 Monday

a. Weekly team conference call at 8PM EST

4. Week 3: October 20 Saturday

a. First draft of each sculpture completed
i. Entire team on point for their own sculptures


b. Update Progress Journal on team Blog site
i. Each member responsible for progress report of no less than 300 words


5. Week 4: October 22 Monday

a. Weekly team conference call at 8PM EST

6. Week 4: October 27 Saturday

a. Final draft of each sculpture completed
i. Entire team on point for their own sculptures


b. Update Progress Journal on team Blog site
i. Each member responsible for progress report of no less than 300 words


7. Week 5: October 29 Monday

a. Weekly team conference call at 8PM EST

1. Week 5: October 31 Wednesday

a. Final draft of sculpture park completed with each member’s sculpture
i. Brian on point for the sculpture park


b. Final Team Reflection notes completed
i. Entire team on point to submit reflection notes to Anthonyette
ii. Anthonyette on point to complete final reflection page


2. Week 5: November 2 Friday

a. Completed version of sculpture park ready for submission
i. Brian on point for sculpture park


b. Completed Team Reflection Page ready for the blog site
i. Anthonyette on point for Reflection Page


c. Sculpture park added to Google Earth
i. Lissette on point to upload our sculpture


d. Blog site added to the Blackboard discussion board
i. Darrell on point to add our website link to blackboard

3 comments:

Prof Wocell said...

Hello team.
I am wondering how you are making out with your sculpture park. You plan looks great and very energetic. How is that all coming along? Are you still using Google Earth in your project?
The dates need to be changed as class will end on 10/31.
Good luck and let me know how you're making out. I will be checking back later,
Prof Wocell

Anonymous said...

Hi Lynn-

We've been hard at work bringing our scultpures to life and getting used to using Sketch Up. We completed the landscape yesterday and have inserted 3 of the 5 sculptures into the park. I am excited at how well it is coming together and can't wait to hear everyone's reation!

Once the park is complete we are going to try our best to add it into Google earth.. wish us luck!

Brian

Prof Wocell said...

Brian,
(and team) You have me on pins and needles waiting to see your work. It sounds so very creative and exciting. I hope you had some help with the journal submissions, it seems like a lot of writing for one person. The reflections are excellent.
Great work team! Bring on the Sculpture Park. By the way everyone, I know personally how difficult the learning curve is for Sketch Up. I give you a lot of credit for sticking with it!!!
Can't wait!
Lynn